Foundation Diagnostic Network Logic · Float · Critical Path
60:00
September Pathfinder Cohort enrolment is open. Reserve your place for the next intake. Pay securely

Session One Assignment · Cohort Pathfinders

Foundation Diagnostic

A focused assignment on the exact areas covered in class: relationship types, network diagrams, early and late dates, total float, free float, critical path, near-critical activities and delay impact.

40Questions
50Marks
60Minutes
Submission deadline: Wednesday 19 August 2026, 11:59 PM UK time. Start early enough to complete and submit before the deadline.
How this works: you receive an instant provisional score and full feedback. Calculation and written reasoning can still be reviewed by Dr Francis before final release.

Garden Office Activity Data

All relationships are Finish-to-Start. Use the activity data to construct the network before completing the pass, float and delay questions.

Day 0 convention: EF = ES + Duration
IDActivityDurPred

Construct it yourself

Draw the Activity-on-Node network from the predecessor data before answering the related questions. The completed logic sequence is intentionally not provided.