Foundation Diagnostic Network Logic · Float · Critical Path
60:00
September Pathfinder Cohort enrolment is open. Reserve your place for the next intake. Pay securely

Session One Assignment · Cohort Pathfinders

Foundation Diagnostic

A focused assignment on the exact areas covered in class: relationship types, network diagrams, early and late dates, total float, free float, critical path, near-critical activities and delay impact.

40Questions
50Marks
60Minutes
Submission deadline: Wednesday 19 August 2026, 11:59 PM UK time. Start early enough to complete and submit before the deadline.
How this works: you receive an instant provisional score and full feedback. Calculation and written reasoning can still be reviewed by Dr Francis before final release.
Part 1 Question 1 of 40

Garden Office Reference Network

All relationships are Finish-to-Start. Use this reference for the network, pass, float and delay questions.

Day 0 convention: EF = ES + Duration
IDActivityDurPred

Logic flow

A · Site set-up2 days
B · Excavate3 days
C · Drainage2 days
D · Base slab4 days
E · Frame and roof5 days
F · External works3 days